Skip to main content

Public contracts of Communauté de communes des Coteaux du Girou · 2021

Construction d’un bâtiment Alae à Montjoire

€61k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 9 September 2021 · ended around September 2022 · 12 months

Who won it

Platrerie BeaufilsSIREN 381771773

Number 7 by amount of the 8 contracts Communauté de communes des Coteaux du Girou published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Construction d’un bâtiment Alae à Montjoire: up to €61k over 12 months, Communauté de communes des Coteaux du Girou 2021 · Qipu