Skip to main content

Public contracts of Communauté de communes des Forêts du Perche · 2022

Travaux mise en séparatif secteur des Evees

Poste de refoulement

€78k
maximum contract amount over 5 years — what was paid on it is not published
Signed on 1 January 2022 · running until about January 2027 · 5 yrs
Ongoing1 Jan 2027

That is at most ~€16k a year on average: a maximum too.

Who won it

Entreprise HabertAutres travaux spécialisés de construction · registered office Billy (41130) · headcount 10 to 19 employees · SIREN 300476181

Number 4 by amount of the 8 contracts Communauté de communes des Forêts du Perche published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.