Skip to main content

Public contracts of Communauté de communes des Gorges de l'Ardèche · 2024

Gros oeuvre maçonneries

€172k
framework agreement: a maximum envelope for orders over 16 months, not spending — what was paid on it is not published
Signed on 22 October 2024 · ended around February 2026 · 16 months

That is at most ~€129k a year on average: a maximum too.

Who won it

Jouve-Villard BTPTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Chambonas (07140) · headcount 10 to 19 employees · SIREN 790812218

The competition

6 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 3 by amount of the 30 contracts Communauté de communes des Gorges de l'Ardèche published for 2024.

Other contracts of Jouve-Villard BTP in Communauté de communes des Gorges de l'Ardèche

Gros Œuvre2024 · maximum over 10 months121€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : 5

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.