Construction d’une salle communautaire Saint Martin d’Abbat

Électricité

€96k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 28 May 2025 · ended around August 2026 · 15 months

That is at most ~€77k a year on average: a maximum too.

Who won it

NormielecTravaux d'installation électrique dans tous locaux · registered office Vienne-En-Val (45510) · headcount 6 to 9 employees · SIREN 495018269

Number 18 by amount of the 26 contracts Communauté de communes des Loges published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.