Public contracts of Communauté de communes des Pays de Cayres et de Pradelles · 2019
Village vances d’alleyras
Maîtrise d’oeuvre
That is at most ~€121k a year on average: a maximum too.
Who won it
Cabinet Chenevier-Mochkovitch (CM Economistes)Ingénierie, études techniques · registered office Saint-Etienne (42000) · headcount 20 to 49 employees · SIREN 509752549A contract awarded to 4 holders; above, the main holder. With it: SARL Jacques Varennes Architecte, B.E.R., Rochard et Associes. The amount is the whole contract’s: the DECP does not publish each holder’s share.
The largest of the 13 contracts Communauté de communes des Pays de Cayres et de Pradelles published for 2019.
Contract details (procedure, price, amendments, lots)
Procedure : Procédure concurrentielle avec négociation
Price : Ferme
Published amendments : 3
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.