Public contracts of Communauté de communes des Rives du Haut Allier · 2023

Audit énergétique des bâtiments de la CCRHA

€49k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 10 July 2023 · ended around July 2025 · 2 yrs

That is at most ~€24k a year on average: a maximum too.

Who won it

Enera ConseilSIREN 492952692

Number 8 by amount of the 11 contracts Communauté de communes des Rives du Haut Allier published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.