Public contracts of Communauté de communes des Vallées d'Auge et du Merlerault · 2026

Isolation et veture de façade-rénovation énergétique école élémentaire Edgar Degas

€244k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 5 June 2026 · running until about January 2027 · 7 months
Ongoing4 Jan 2027

Company selected

Isor BTPConstruction de maisons individuelles · registered office Val-De-Reuil (27100) · headcount 10 to 19 employees · SIREN 842790545

The competition

9 bids received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 2 by amount of the 13 contracts Communauté de communes des Vallées d'Auge et du Merlerault published for 2026.

Other contracts of Isor BTP in Communauté de communes des Vallées d'Auge et du Merlerault

Rénovation énergétique de l’école élementaire Edgar Degas à Gacé2026 · maximum over 7 months293€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Isolation et veture de façade-rénovation énergétique école…: up to €244k over 7 months, Communauté de communes des Vallées d'Auge et du Merlerault 2026 · Qipu