Skip to main content

Public contracts of Communauté de communes Dombes Saône Vallée · 2024

Mise en séparatif réseaux ass chemin gourlas fareins

€220k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 7 August 2024 · ended around December 2024 · 4 months

Company selected

SocaflTravaux de terrassement courants et travaux préparatoires · registered office Crottet (01290) · headcount 50 to 99 employees · SIREN 686750373

The competition

7 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 21 by amount of the 54 contracts Communauté de communes Dombes Saône Vallée published for 2024.

Other contracts of Socafl in Communauté de communes Dombes Saône Vallée

Travaux pour la mise en séparatif des réseaux d’assainissement Rue des…2022 · maximum over 7 months604€kTravaux pour la mise en séparatif des réseaux d’assainissement…2020 · maximum over 17 months984€kTravaux pour l’évacuation de remblais aux abords de la station…2020 · maximum over 3 months69€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 4

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.