Skip to main content

Public contracts of Communauté de communes du Bassin d'Aubenas · 2026

Travaux neufs et de modernisation de voirie

€1M
framework agreement: a maximum envelope for orders over 3 years, not spending — what was paid on it is not published
Signed on 8 July 2026 · running until about July 2029 · 3 yrs
Ongoing8 Jul 2029

That is at most ~€333k a year on average: a maximum too.

Company selected

Eurovia Drôme Ardèche Loire AuvergneConstruction de routes et autoroutes · registered office Saint-Jean-Bonnefonds (42650) · headcount 500 to 999 employees · SIREN 317975910

The competition

4 bids received

Median for this procedure in 2026: 3 bids, across 23502 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 4 by amount of the 14 contracts Communauté de communes du Bassin d'Aubenas published for 2026.

Other contracts of Eurovia Drôme Ardèche Loire Auvergne in Communauté de communes du Bassin d'Aubenas

Travaux voie verte St Sernin Aubenas2023 · maximum over 10 months178€kTravaux neufs et modernisation de voirie eurovia2022 · maximum over 4 years1€MTravaux aménagement voie verte Labégude Lalevade2021 · maximum over 10 months762€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Forfaitaire

Published amendments : none

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.