Skip to main content

Public contracts of Communauté de communes du Canton d'Erstein · 2023

Maîtrise d’oeuvre pour la construction d’un périscolaire en bâtiments modulaires sur le site de l’École Rohan à Benfeld

€65k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 23 March 2023 · ended around March 2025 · 2 yrs

That is at most ~€33k a year on average: a maximum too.

Who won it

Atelier Architecture Christophe CunciSIREN 481162519

Number 59 by amount of the 68 contracts Communauté de communes du Canton d'Erstein published for 2023.

Other contracts of Atelier Architecture Christophe Cunci in Communauté de communes du Canton d'Erstein

Maîtrise d’oeuvre pour la construction d’un périscolaire en bâtiments…2024 · maximum over 14 months156€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.