Skip to main content

Public contracts of Communauté de communes du Golfe de Saint-Tropez · 2021

Travaux de réhabilitation de l’escalier communal Bailli de Suffren

Commune du rayol canadel sur mer

€1.1M
maximum contract amount over 14 months — what was paid on it is not published
Signed on 20 October 2021 · ended around December 2022 · 14 months

That is at most ~€980k a year on average: a maximum too.

Who won it

Freyssinet FranceAutres travaux spécialisés de construction · registered office Rueil-Malmaison (92500) · headcount 500 to 999 employees · SIREN 334057361

A contract awarded to 2 holders; above, the main holder. With it: T.P. Geo. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 7 by amount of the 65 contracts Communauté de communes du Golfe de Saint-Tropez published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : 3

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.