Skip to main content

Public contracts of Communauté de communes du Grand Pontarlier · 2019

Réalisation d’une etude de faisabilité pour la création d’un bassin d’orage sur la station d’épuration de Doubs

€56k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 3 June 2019 · ended around November 2019 · 5 months

Who won it

BG Ingenieurs ConseilsIngénierie, études techniques · registered office Paris (75012) · headcount 200 to 249 employees · SIREN 303559249

Number 16 by amount of the 27 contracts Communauté de communes du Grand Pontarlier published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.