Rénovation du système de chauffage du siège de la CCHB

Plâtrerie peinture menuiseries intérieures

€62k
contract ceiling — what was paid on it is not published
Signed on 27 June 2023 · ended around December 2023 · 6 months

Who won it

Entreprise BordattoTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Oloron-Sainte-Marie (64400) · headcount 20 to 49 employees · SIREN 046780052

The competition

10 bids received

awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 29 by amount of the 41 contracts Communauté de communes du Haut Béarn published for 2023.

Other contracts of Entreprise Bordatto in Communauté de communes du Haut Béarn

Réhabilitation de l’aile nord de la cité administrative…202629€kTravaux d’agrandissement de l’espace jeliote…2021113€kRestructuration du centre de ski nordique du COL du somport. d’une…2020808€k
Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no