Skip to main content

Public contracts of Communauté de communes du Pays de l'Ourcq · 2022

Ms1 construction de la station d’épuration de marcilly

€99k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 18 May 2022 · ended around November 2023 · 18 months

That is at most ~€66k a year on average: a maximum too.

Who won it

Setec HydratecIngénierie, études techniques · registered office Paris (75012) · headcount 200 to 249 employees · SIREN 301392569

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Atelier 251 (A 251). The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 7 by amount of the 12 contracts Communauté de communes du Pays de l'Ourcq published for 2022.

Other contracts of Setec Hydratec in Communauté de communes du Pays de l'Ourcq

Ms13 reconstruction du réservoir sur tour d’eau potable de…2025 · maximum over 15 months132€kMs12 reconstruction du réservoir sur tour d’eau potable de la trousse a…2025 · maximum over 15 months91€kDoublement de la filière boues de la station d’épuration de LIZY…2025 · maximum over 2.5 years84€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.