Public contracts of Communauté de communes du Pays des Herbiers · 2024

Mission d’assistance à maîtrise d’ouvrage pour le schéma directeur des énergies renouvelables : organiser et déployer le mix énergétique local…

€31k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 12 December 2024 · ended around August 2025 · 8 months

Who won it

AkajouleIngénierie, études techniques · registered office Saint-Nazaire (44600) · headcount 20 to 49 employees · SIREN 521436949

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 49 by amount of the 65 contracts Communauté de communes du Pays des Herbiers published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.