Public contracts of Communauté de communes du Pays Fouesnantais · 2025

Travaux de modernisation, de renforcement ou d’extension des installations d’éclairage public sur l’ensemble du territoire de la Communauté de communes du Pays…

Travaux de…

€550k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 16 July 2025 · running until about July 2029 · 4 yrs
Ongoing16 Jul 2029

That is at most ~€138k a year on average: a maximum too.

Who won it

Garczynski Traploir CornouailleConstruction de réseaux électriques et de télécommunications · registered office Concarneau (29900) · headcount 20 to 49 employees · SIREN 443976378

The competition

3 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 16 by amount of the 83 contracts Communauté de communes du Pays Fouesnantais published for 2025.

Other contracts of Garczynski Traploir Cornouaille in Communauté de communes du Pays Fouesnantais

Travaux éclairage public2025 · maximum over 4 years2.4€MTravaux éclairage public2025 · maximum over 4 years2.2€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.