Construction d’un accueil périscolaire à Bindernheim

Bardage briques

€38k
maximum contract amount over 22 months — what was paid on it is not published
Signed on 10 March 2026 · running until about January 2028 · 22 months
Ongoing9 Jan 2028

That is at most ~€21k a year on average: a maximum too.

Who won it

Entreprise de Construction DervovicTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Hurtigheim (67117) · headcount 10 to 19 employees · SIREN 485030712

The competition

1 bid received

Median for this procedure in 2026: 3 bids, across 20741 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 15 by amount of the 24 contracts Communauté de communes du Ried de Marckolsheim published for 2026.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.