Skip to main content

Public contracts of Communauté de communes Entre Bièvre et Rhône · 2025

Travaux sur les réseaux humides sur le territoire Entre Bièvre Et Rhône

€1.3M
maximum contract amount over 12 months — what was paid on it is not published
Signed on 3 April 2025 · ended around April 2026 · 12 months

Company selected

Rampa Travaux PublicsConstruction de réseaux pour fluides · registered office Le Pouzin (07250) · headcount 250 to 499 employees · SIREN 323468991

A contract awarded to 5 holders; above, the main holder. With it: Mounard TP, Sogea Rhone-Alpes (Agence de Valence), Montagnier TP, Moutot Genie Civil. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

11 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 5 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 99 contracts Communauté de communes Entre Bièvre et Rhône published for 2025.

Other contracts of Rampa Travaux Publics in Communauté de communes Entre Bièvre et Rhône

Petits travaux sur les réseaux d’eau ou d’assainissement2026 · maximum over 12 months15€MMapa 2026 11-St Maurice Mata Buissard Louise Michel2026 · maximum over 6 months577€kMS04-St Clair du Rhône Rue Berthelot2026 · maximum over 3 months86€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.