Skip to main content

Public contracts of Communauté de communes Entre Saône et Grosne · 2023

Électricité

€49k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 7 February 2023 · ended around February 2024 · 12 months

Who won it

SochalegTravaux d'installation électrique dans tous locaux · registered office Chalon-Sur-Saone (71100) · headcount 20 to 49 employees · SIREN 306906355

Number 20 by amount of the 25 contracts Communauté de communes Entre Saône et Grosne published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.