Public contracts of Communauté de communes Entre Saône et Grosne · 2023

Gros œuvre

€141k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 7 February 2023 · ended around February 2024 · 12 months

Who won it

Nowacki ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Cuisery (71290) · headcount 6 to 9 employees · SIREN 394051668

Number 9 by amount of the 25 contracts Communauté de communes Entre Saône et Grosne published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.