Skip to main content

Public contracts of Communauté de communes Haut Val de Sèvre · 2023

Travaux de sectorisation sur réseau d’eau potable

€426k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 1 December 2023 · ended around April 2024 · 4 months

Who won it

TtpiTravaux de terrassement courants et travaux préparatoires · registered office Frontenay-Rohan-Rohan (79270) · headcount 20 to 49 employees · SIREN 530773746

The competition

4 bids received

Median for this procedure in 2023: 3 bids, across 8300 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 2 by amount of the 5 contracts Communauté de communes Haut Val de Sèvre published for 2023.

Other contracts of Ttpi in Communauté de communes Haut Val de Sèvre

Réalisation de travaux neufs, de réparations…2026 · maximum over 12 months250€kProblematique CVM2025 · maximum over 8 months1.1€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.