Skip to main content

Public contracts of Communauté de communes Les Avant-Monts · 2025

Accord cadre à BDC

Travaux et interventions ponctuelles liés à l’exploitation en régie des réseaux EU

€168k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 11 July 2025 · running until about July 2029 · 4 yrs
Ongoing11 Jul 2029

That is at most ~€42k a year on average: a maximum too.

Who won it

SaurCaptage, traitement et distribution d'eau · registered office Issy-Les-Moulineaux (92130) · headcount 5,000 to 9,999 employees · SIREN 339379984

A contract awarded to a consortium of 2 holders; above, the main holder. With it: TP Bessiere. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

3 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 2 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 15 by amount of the 32 contracts Communauté de communes Les Avant-Monts published for 2025.

Other contracts of Saur in Communauté de communes Les Avant-Monts

Construction nouvelle station d’épuration2025 · maximum over 15 months1.6€MAccord cadre à BDC2025 · maximum over 4 years72€kRéhabilitation de la station d’épuration de roujan2023 · maximum over 15 months1.7€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.