Skip to main content

Public contracts of Communauté de communes Maine Cœur de Sarthe · 2019

Viabilisation de la zone d’activités Champfleury 3 à La Bazoge

€30k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 11 July 2019 · ended around September 2019 · 2 months

Who won it

Bouygues Énergies & ServicesTravaux d'installation électrique sur la voie publique · registered office Guyancourt (78280) · headcount 2,000 to 4,999 employees · SIREN 775664873

Number 17 by amount of the 25 contracts Communauté de communes Maine Cœur de Sarthe published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.