Maîtrise d’œuvre travaux sur les infrastructures d’eau potable

€3M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 25 April 2024 · running until about April 2028 · 4 yrs
Ongoing25 Apr 2028

That is at most ~€750k a year on average: a maximum too.

Who won it

Socama IngenierieIngénierie, études techniques · registered office Le Haillan (33185) · headcount 50 to 99 employees · SIREN 317308518

A contract awarded to a consortium of 3 holders; above, the main holder. With it: Ameau Ingenierie, EGIS Eau SA. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

5 bids received

Median for this procedure in 2024: 3 bids, across 17585 comparable contracts. Open tender · awarded to 3 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

The largest of the 14 contracts Communauté de communes Médoc Estuaire published for 2024.

Other contracts of Socama Ingenierie in Communauté de communes Médoc Estuaire

Maîtrise d’œuvre pour les travaux sur les infrastructures d’eau potable…2024 · maximum over 4 years1.5€MMaîtrise d’œuvre pour les travaux sur les infrastructures d’eau potable…2024 · maximum over 4 years750€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.