Public contracts of Communauté de communes Montfort Communauté · 2025

Aménagement du Parc d’activités de la Nouette II sur la commune de Breteil

Terrassement · Voirie · Assainissement EU et EP

€496k
maximum contract amount over 17 months — what was paid on it is not published
Signed on 25 March 2025 · ended around August 2026 · 17 months

That is at most ~€350k a year on average: a maximum too.

Company selected

Perotin Travaux PublicsTravaux de terrassement courants et travaux préparatoires · registered office Breteil (35160) · headcount 20 to 49 employees · SIREN 432112738

The competition

1 bid received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 31 contracts Communauté de communes Montfort Communauté published for 2025.

Other contracts of Perotin Travaux Publics in Communauté de communes Montfort Communauté

Aménagement des rues de l’Auze et de Bedee a pleumeleuc2025 · maximum over 5 months482€kAménagement des rues de l’Auze et de Bédée sur la commune de Pleumeleuc2025 · maximum over 21 months477€kAménagement pa nouette ii breteil2025 · maximum over 4 months458€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.