Skip to main content

Public contracts of Communauté de communes Moselle et Madon · 2019

Aménagement de la zac Filinov-2e tranche

Voirie et réseaux

€1.6M
maximum contract amount over 10 months — what was paid on it is not published
Signed on 3 June 2019 · ended around April 2020 · 10 months

Company selected

Ipf 54Construction de routes et autoroutes · registered office Nancy (54000) · SIREN 329198337

The largest of the 36 contracts Communauté de communes Moselle et Madon published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Aménagement de la zac Filinov-2e tranche: up to €1.6M over 10 months, Communauté de communes Moselle et Madon 2019 · Qipu