Skip to main content

Public contracts of Communauté de communes Pays de Chantonnay · 2024

Travaux de réhabilitation partielle et extension de l’Ehpad les erables

Électricité courants forts et faibles

€463k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 14 June 2024 · running until about April 2027 · 3 yrs
Ongoing15 Apr 2027

That is at most ~€163k a year on average: a maximum too.

Company selected

B.L.I.Travaux d'installation électrique dans tous locaux · registered office La Chaize-Le-Vicomte (85310) · headcount 50 to 99 employees · SIREN 381865229

The competition

4 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 6 by amount of the 55 contracts Communauté de communes Pays de Chantonnay published for 2024.

Other contracts of B.L.I. in Communauté de communes Pays de Chantonnay

Courants forts et faibles2025 · maximum over 17 months278€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.