Skip to main content

Public contracts of Communauté de communes Pays de Nay · 2026

Rénovation et extension de la déchetterie d’Assat

Charpente couverture zinguerie bardage

€135k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 24 March 2026 · running until about March 2027 · 12 months
Ongoing24 Mar 2027

Who won it

Les Charpentiers Concepteurs BoisTravaux de charpente · registered office Oloron-Sainte-Marie (64400) · headcount 10 to 19 employees · SIREN 444842702

Number 13 by amount of the 27 contracts Communauté de communes Pays de Nay published for 2026.

Other contracts of Les Charpentiers Concepteurs Bois in Communauté de communes Pays de Nay

Travaux de construction d’un centre culturel communautaire médiathèque…2022 · maximum over 22 months288€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.