Skip to main content

Public contracts of Communauté de communes Piège Lauragais Malepère · 2022

Travaux de mise en place d’un dessableur sur la commune de Bram

€136k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 25 July 2022 · ended around July 2025 · 3 yrs

That is at most ~€45k a year on average: a maximum too.

Company selected

SaurCaptage, traitement et distribution d'eau · registered office Issy-Les-Moulineaux (92130) · headcount 5,000 to 9,999 employees · SIREN 339379984

A contract awarded to 3 holders; above, the main holder. With it: SARL Associes Sales, Entreprise David. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 2 by amount of the 2 contracts Communauté de communes Piège Lauragais Malepère published for 2022.

Other contracts of Saur in Communauté de communes Piège Lauragais Malepère

Marché subséquent 2024EAU1 BDC3 Travaux de renouvellement des…2025 · maximum over 12 months305€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Travaux de mise en place d’un dessableur sur la commune de Bram: up to €136k over 3 years, Communauté de communes Piège Lauragais Malepère 2022 · Qipu