Public contracts of Communauté de communes Roche aux Fées Communauté · 2025
Outil de supervision pour la Gestion Technique des Bâtiments (GTB)
That is at most ~€12k a year on average: a maximum too.
Who won it
High Tech For Telecontrol Project (HTTP)Ingénierie, études techniques · registered office Redon (35600) · headcount 6 to 9 employees · SIREN 888490455The competition
Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
Number 12 by amount of the 33 contracts Communauté de communes Roche aux Fées Communauté published for 2025.
Other contracts of High Tech For Telecontrol Project (HTTP) in Communauté de communes Roche aux Fées Communauté
Installation de systèmes de gestion technique des bâtiments (GTB)…2025 · maximum over 18 months80€kAchat d’un outil de supervision pour la Gestion Technique des Bâtiments…2025 · maximum over 4 years46€kContract details (procedure, price, amendments, lots)
Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds
Price : Mixte
Published amendments : 1
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.