Skip to main content

Public contracts of Communauté de communes Vallées de l'Orne et de l'Odon · 2019

Construction de l’équipement touristique du pont du coudray

Électricité courants forts & courants faibles

€156k
maximum contract amount over 17 months — what was paid on it is not published
Signed on 14 October 2019 · ended around March 2021 · 17 months

That is at most ~€110k a year on average: a maximum too.

Who won it

Destais SASSIREN 310531868

Number 7 by amount of the 14 contracts Communauté de communes Vallées de l'Orne et de l'Odon published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.