2022 Ac bc gros oeuvre bâtiment 2022-2025

€1M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 15 November 2021 · ended around November 2025 · 4 yrs

That is at most ~€250k a year on average: a maximum too.

Who won it

Rabot Dutilleul ConstructionConstruction d'autres bâtiments · registered office Wasquehal (59290) · headcount 500 to 999 employees · SIREN 389612383

Number 13 by amount of the 85 contracts Communauté urbaine d'Arras published for 2021.

Other contracts of Rabot Dutilleul Construction in Communauté urbaine d'Arras

Tx SDS giraudon2023 · maximum over 3 months176€k2023 Ac bc gros oeuvre bâtiment2022 · maximum over 4 years1.6€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.