Skip to main content

Public contracts of Dijon Métropole · 2020

Travaux de renouvellement de réseaux d’eau potable sur les communes de Daix et Fontaine les Dijon

€159k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 25 June 2020 · ended around June 2021 · 12 months

Who won it

B.E.R. 21SIREN 440203693

Number 41 by amount of the 76 contracts Dijon Métropole published for 2020.

Other contracts of B.E.R. 21 in Dijon Métropole

Dijon Métropole2025 · maximum over 12 months76€kDijon Métropole2024 · maximum over 11 months82€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.