Études préalables à la restauration de la Souffel entre Bischheim et La Wantzenau

€15k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 29 January 2025 · running until about January 2029 · 4 yrs
Ongoing29 Jan 2029

That is at most ~€4k a year on average: a maximum too.

Company selected

Sinbio SCOPIngénierie, études techniques · registered office Selestat (67600) · headcount 20 to 49 employees · SIREN 877737742

The competition

3 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 453 by amount of the 528 contracts Eurométropole de Strasbourg published for 2025.

Other contracts of Sinbio SCOP in Eurométropole de Strasbourg

Maîtrise d’œuvre pour la restauration écologique du Fossé des Remparts…2025 · maximum over 3 years101€kMaîtrise d’œuvre pour le projet de restauration de l’Ehn à Geispolsheim2025 · maximum over 4 years50€kÉtude globale des cours d’eau et des zones humides du bassin versant de…2025 · maximum over 2 years36€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.