Travaux mur soutènement chemin Lateral-Travaux de réfection du mur, du perré et des garde-corps situes Chemin latéral à Alfortville

€388k
maximum contract amount over 1 month — what was paid on it is not published
Signed on 25 September 2019 · ended around October 2019 · 1 month

Company selected

France Travaux (VRD)Construction de réseaux pour fluides · registered office Valenton (94460) · headcount 50 to 99 employees · SIREN 343818688

Number 41 by amount of the 127 contracts Grand Paris Sud Est Avenir published for 2019.

Other contracts of France Travaux (VRD) in Grand Paris Sud Est Avenir

Travaux assainissement et voirie-Travaux d’entretien…2023 · maximum over 4 years14.4€MTravaux assainissement et voirie-Travaux de réhabilitation sans…2023 · maximum over 4 years5.6€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.