Public contracts of Grenoble-Alpes-Métropole · 2025

Étude de déconnexion des eaux pluviales du réseau d’assainissement

€258k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 28 April 2025 · running until about April 2027 · 2 yrs
Ongoing29 Apr 2027

That is at most ~€129k a year on average: a maximum too.

Who won it

EGIS Eau SAIngénierie, études techniques · registered office Montpellier (34000) · headcount 200 to 249 employees · SIREN 493378038

The competition

3 bids received

Median for this procedure in 2025: 3 bids, across 17964 comparable contracts. Open tender · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 61 by amount of the 132 contracts Grenoble-Alpes-Métropole published for 2025.

Other contracts of EGIS Eau SA in Grenoble-Alpes-Métropole

Maîtrise d’oeuvre pour travaux sur ouvrages d’eau potable…2025 · maximum over 4 years800€kAnalyse des Risques de Défaillance (ARD) du système de collecte…2022 · maximum over 4 months34€kMaîtrise d’oeuvre relative aux travaux de sécurisation des digues de…2021 · maximum over 2 years40€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Mixte

Published amendments : 1

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale