Public contracts of Grenoble-Alpes-Métropole · 2022

Travaux pour le renforcement de la capacité de pompage des stations Fontenay 1 et Fontenay 2

€1.1M
maximum contract amount over 6 months — what was paid on it is not published
Signed on 28 March 2022 · ended around September 2022 · 6 months

Who won it

Est OuvragesConstruction d'ouvrages d'art · registered office Atton (54700) · headcount 100 to 199 employees · SIREN 439744996

Number 10 by amount of the 101 contracts Grenoble-Alpes-Métropole published for 2022.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none