Skip to main content

Public contracts of LBN Communauté · 2021

Maîtrise d’oeuvre construction MSP Chantenay

€45k
contract ceiling — what was paid on it is not published
Signed on 15 April 2021 · ended around April 2023 · 2 yrs

Who won it

StbatSIREN 509520565

Main holder, with the largest amount. The contract has 5 holders; the others are not shown here yet.

Number 10 by amount of the 12 contracts LBN Communauté published for 2021.

Other contracts of Stbat in LBN Communauté

Maîtrise d’oeuvre Extension MSP Coulans202154€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.