Public contracts of Métropole d'Aix-Marseille-Provence · 2024

Secteur bassin ouest Berre-l’etang, bouc-bel-air, cabriès, coudoux, eguilles, la fare-les-oliviers, lançonprovence, les pennesmirabeau, pertuis…

€3.4M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 12 December 2024 · running until about December 2028 · 4 yrs
Ongoing12 Dec 2028

That is at most ~€840k a year on average: a maximum too.

Company selected

Entreprise Gle Électricité Noel BerangerTravaux d'installation électrique sur la voie publique · registered office La Penne-Sur-Huveaune (13821) · headcount 50 to 99 employees · SIREN 072802689

A contract awarded to a consortium of 3 holders; above, the main holder. With it: Électricité Marseille Illuminations Eclairage, Ineo Réseaux Sud (Equans). The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

7 bids received

Median for this procedure in 2024: 3 bids, across 17585 comparable contracts. Open tender · awarded to 3 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 81 by amount of the 773 contracts Métropole d'Aix-Marseille-Provence published for 2024.

Other contracts of Entreprise Gle Électricité Noel Beranger in Métropole d'Aix-Marseille-Provence

Aménagement du boulevard des Dames entre l’avenue R. Schuman…2026 · maximum over 2.5 years223€kÉclairage public2025 · maximum over 6 months45€kExploitation maintien et petits Travaux de rénovation…2024 · maximum over 4 years10.4€M
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Social considerations : Clause sociale

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.