Public contracts of Métropole Rouen Normandie · 2024

Rénovation énergétique et environnementale de l’immeuble Couperin à Rouen

€722k
maximum contract amount over 21 months — what was paid on it is not published
Signed on 17 April 2024 · ended around January 2026 · 21 months

That is at most ~€412k a year on average: a maximum too.

Company selected

Poixblanc Charpentes (PBC Construction)Travaux de charpente · registered office Neufchatel-En-Bray (76270) · headcount 10 to 19 employees · SIREN 422512699

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 64 by amount of the 195 contracts Métropole Rouen Normandie published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.