Skip to main content

Public contracts of Métropole Rouen Normandie · 2024

Saint Sever Nouvelle Gare

Étude hydraulique pour caractériser le risque et accompagner l’aide à la décision

€107k
maximum contract amount over 6 months — what was paid on it is not published
Signed on 30 December 2024 · ended around July 2025 · 6 months

Who won it

ArteliaIngénierie, études techniques · registered office Saint-Ouen-Sur-Seine (93400) · headcount 2,000 to 4,999 employees · SIREN 444523526

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 48385 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 154 by amount of the 195 contracts Métropole Rouen Normandie published for 2024.

Other contracts of Artelia in Métropole Rouen Normandie

Maîtrise d’oeuvre pour la mise à niveau de l’usine d’eau potable de…2022 · maximum over 6 years290€kMaîtrise d’oeuvre pour la mise à niveau de l’usine d’eau potable du…2022 · maximum over 5 years193€kÉtude des risques de pollution liés aux inondations2022 · maximum over 10 months60€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.