Skip to main content

Public contracts of Montpellier Méditerranée Métropole · 2024

Travaux de construction du bâtiment annexe de l’Ecolothèque

€786
maximum contract amount over 13 months — what was paid on it is not published
Signed on 20 December 2024 · ended around January 2026 · 13 months

That is at most ~€726 a year on average: a maximum too.

Company selected

STE des Ets Serrano (Établissements Serrano)Travaux d'installation d'eau et de gaz en tous locaux · registered office Villeneuve-Les-Maguelone (34750) · headcount 6 to 9 employees · SIREN 353186570

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48741 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 253 by amount of the 253 contracts Montpellier Méditerranée Métropole published for 2024.

Other contracts of STE des Ets Serrano (Établissements Serrano) in Montpellier Méditerranée Métropole

Ecolotheque2024 · maximum over 15 months150€kTravaux de maintenance et de grosses réparations des équipements génie…2022 · maximum over 4 years4.8€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 3

Subcontracting declared : no

Social considerations : Critère social

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.