Travaux de diagnostic, d’entretien, de réparation et de rénovation des Rails du train du parc floral de la source

€100k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 7 January 2021 · ended around January 2025 · 4 yrs

That is at most ~€25k a year on average: a maximum too.

Who won it

Edc TerrassementSIREN 491775854

A contract awarded to a consortium of 2 holders; above, the main holder. With it: Partenarail. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

4 bids received

Median for this procedure in 2021: 3 bids, across 1019 comparable contracts. Simplified procedure · awarded to 2 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 178 by amount of the 246 contracts Orléans Métropole published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Mixte

Published amendments : 9

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.