Maîtrise d’œuvre pour la construction d’un bassin de stockage/restitution de 10 000 m³ sur la commune de la chapelle saint mesmin

€463k
framework agreement: a maximum envelope for orders over 3 years, not spending — what was paid on it is not published
Signed on 16 December 2024 · running until about January 2028 · 3 yrs
Ongoing16 Jan 2028

That is at most ~€150k a year on average: a maximum too.

Who won it

ArteliaIngénierie, études techniques · registered office Saint-Ouen-Sur-Seine (93400) · headcount 2,000 to 4,999 employees · SIREN 444523526

A contract awarded to 4 holders; above, the main holder. With it: Traitclair, Laba Territoires (Agence Hamelin), Laba. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

3 bids received

Median for this procedure in 2024: 3 bids, across 664 comparable contracts. Procedure with negotiation · awarded to 4 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 41 by amount of the 199 contracts Orléans Métropole published for 2024.

Other contracts of Artelia in Orléans Métropole

Maîtrise d’oeuvre pour la construction de la passerelle saint nicolas a…2025 · maximum over 4 years268€kAssistance a la maîtrise d’ouvrage pour l’elaboration d’un dossier loi…2024 · maximum over 19 months156€kDiagnostic faune/flore2024 · maximum over 15 months96€k
Contract details (procedure, price, amendments, lots)

Procedure : Procédure avec négociation

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Mixte

Published amendments : 3

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.