Voirie et Réseaux Divers, éclairage public

€446k
framework agreement: a maximum envelope for orders over 3 years, not spending — what was paid on it is not published
Signed on 3 June 2025 · running until about June 2028 · 3 yrs
Ongoing3 Jun 2028

That is at most ~€149k a year on average: a maximum too.

Who won it

PrunevieilleTravaux d'installation électrique sur la voie publique · registered office Saint-Denis (93200) · headcount 100 to 199 employees · SIREN 410543813

A contract awarded to a consortium of 3 holders; above, the main holder. With it: Bourgeois Entreprise Travaux Publics, Dubrac T.P.. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

5 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 3 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 72 by amount of the 138 contracts Plaine Commune published for 2025.

Other contracts of Prunevieille in Plaine Commune

Éclairage2025 · maximum over 15 months82€kMaintenance des installations d’éclairage public et des métiers connexes2023 · maximum over 12 months30€MÉclairage public2023 · maximum over 3 years185€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : 5

Subcontracting declared : yes

Social considerations : Clause sociale, Critère social

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.