Skip to main content

Public contracts of Saint-Etienne Métropole · 2024

Réhabilitation du réservoir d’eau potable du Bessy à Saint-Paul-en-Jarez

€148k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 10 July 2024 · ended around January 2026 · 18 months

That is at most ~€99k a year on average: a maximum too.

Company selected

Sade - Compagnie Générale de Travaux HydrauliquesConstruction de réseaux pour fluides · registered office Paris (75014) · headcount 2,000 to 4,999 employees · SIREN 562077503

The competition

5 bids received

Median for this procedure in 2024: 3 bids, across 48340 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 130 by amount of the 270 contracts Saint-Etienne Métropole published for 2024.

Other contracts of Sade - Compagnie Générale de Travaux Hydrauliques in Saint-Etienne Métropole

Travaux de mise en séparatif de réseaux d’assainissement…2026 · maximum over 9 months2.7€MTravaux de création d’un collecteur de transfert d’assainissement en…2026 · maximum over 13 months1.5€MTravaux de raccordement d’une partie des effluents du centre ville de…2026 · maximum over 8 months662€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Critère social, Clause sociale

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.