Skip to main content

Public contracts of Toulouse Métropole · 2024

CV Travaux d’aménagement du Parvis Brienne Saint-Pierre

€161k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 4 June 2024 · ended around September 2025 · 15 months

That is at most ~€129k a year on average: a maximum too.

Who won it

Husson InternationalFabrication de structures métalliques et de parties de structures · registered office Lapoutroie (68650) · headcount 50 to 99 employees · SIREN 321154320

The competition

1 bid received

Median for this procedure in 2024: 3 bids, across 17585 comparable contracts. Open tender · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 173 by amount of the 276 contracts Toulouse Métropole published for 2024.

Other contracts of Husson International in Toulouse Métropole

Marché subséquent n° 5 : création d’un city stade au sein du stade Rigal2026 · maximum over 12 months80€kMarché subséquent n°3 : création d’un city stade au parc des sept…2024 · maximum over 3 months53€kTravaux de réalisation d’équipements sportifs de plein air en accès…2022 · maximum over 4 years154€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Critère social, Clause sociale, Marché réservé

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.