Travaux de dévoiement sans tranchée du pont route de Saint-Jory

Commune de Saint-Jory · Réalisation d’un micro tunnelier sous voies SNCF et canal VNF pour la pose de réseau AEP et EU…

€1.5M
maximum contract amount over 8 months — what was paid on it is not published
Signed on 20 February 2025 · ended around October 2025 · 8 months

Who won it

BessacSIREN 301589347

The competition

5 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 45 by amount of the 319 contracts Toulouse Métropole published for 2025.

Other contracts of Bessac in Toulouse Métropole

Travaux de dévoiement sans tranchée du pont route de saint Jory2022 · maximum over 7 months1.5€MCugnaux-travaux EU collecteur de transfert2022 · maximum over 18 months1.4€MTravaux d’assainissement d’eaux usées2022 · maximum over 12 months1.1€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Critère social, Clause sociale

Environmental considerations : Critère environnemental, Clause environnementale