Nevers: spending by policy area · 2025
Culture, sport and youth
€10.2M
13% of 2025 spending · €300 per resident
€7M in 2024
Breakdown of this item’s spending
Click a line to see what it is made of
The 4 other items (6%)
Largest works since 2023
Click a building site to see the contract
- Rénovation de la piste d’athlétisme du stade Léo Lagrange2025 · 2 contracts€2.8M
- Désamiantage, curage et démolition pour la réhabilitation de la piscine des bords de Loire2023 · 3 contracts · 3 companies€443k
- Requalification du site de l’ancienne piscine des bords de loire a Nevers2025 · 4 contracts · 4 companies€419k
Who won this item’s contracts since 2023
Compared with towns of the same size
14.5% of the town’s running costs goes to this item. Towns of the same size: 20.3%.