Nevers: spending by policy area · 2025
Streets and transport
€4.1M
5% of 2025 spending · €121 per resident
€2.3M in 2024
Breakdown of this item’s spending
Click a line to see what it is made of
Largest works since 2023
Click a building site to see the contract
- Zone commerçante François Mitterrand, phase 1 : voirie, réseaux divers et mobilier2024 · Ipf 54€1.8M
- Aménagement d’une partie de la route départementale 907, quartier du Banlay2023 · 2 contracts · 2 companies€1.3M
- Travaux de comblement de la trémie et de requalification des rues Gustave Flaubert et Honoré de Balzac, dans le cadre du Projet de Renouvellement Urbain du…2025 · 3 contracts · 3 companies€1M
Who won this item’s contracts since 2023
Compared with towns of the same size
1.7% of the town’s running costs goes to this item. Towns of the same size: 2.2%.
Source: the town’s 2025 accounts (DGFiP), by public policy. Amounts paid in the year. Works and companies: published contracts, amounts at signature. See the source